      @BRRABill said:

      @JaredBusch said:

      Why would it be hard? You know that you plugged in 4 servers into each rail. Each PS is 500W. So each rail has 2kW.

      Do you always have each rack pre-filled with servers?

      I was thinking where you had 1 server or 2 in a rack. Do you buy capacity for now, or when the rack is filled?

      You plan your capacity on what you have or realistically expect to get in the near term. always. You don't plan for some unknown future amount of servers.

      BRRABillB 1 Reply Last reply Reply Quote 0
      • MattSpellerM
        MattSpeller @BRRABill
        last edited by

        @BRRABill said:

        @JaredBusch said:

        Why would it be hard? You know that you plugged in 4 servers into each rail. Each PS is 500W. So each rail has 2kW.

        Do you always have each rack pre-filled with servers?

        I was thinking where you had 1 server or 2 in a rack. Do you buy capacity for now, or when the rack is filled?

        For UPS it's best to talk to the business and see what their plans are. You know you need batteries for the things every 3 years and that's a good time to swap out if you need bigger (bigger being the only real reason to change UPS).

        JaredBuschJ 1 Reply Last reply Reply Quote 0
        • BRRABillB
          BRRABill @JaredBusch
          last edited by

          @JaredBusch said:

          You plan your capacity on what you have or realistically expect to get in the near term. always. You don't plan for some unknown future amount of servers.

          I guess I was thinking the Enterprise folk were always welcoming new servers into the fold.

          😃

          MattSpellerM 1 Reply Last reply Reply Quote 0
          • JaredBuschJ
            JaredBusch @MattSpeller
            last edited by

            @MattSpeller said:

            @BRRABill said:

            @JaredBusch said:

            Why would it be hard? You know that you plugged in 4 servers into each rail. Each PS is 500W. So each rail has 2kW.

            Do you always have each rack pre-filled with servers?

            I was thinking where you had 1 server or 2 in a rack. Do you buy capacity for now, or when the rack is filled?

            For UPS it's best to talk to the business and see what their plans are. You know you need batteries for the things every 3 years and that's a good time to swap out if you need bigger (bigger being the only real reason to change UPS).

            Not just for UPS. this is always best advice. you never buy things for future. You buy for what you need and a realistic expectation of growth.

            1 Reply Last reply Reply Quote 1
            • MattSpellerM
              MattSpeller @BRRABill
              last edited by

              @BRRABill said:

              @JaredBusch said:

              You plan your capacity on what you have or realistically expect to get in the near term. always. You don't plan for some unknown future amount of servers.

              I guess I was thinking the Enterprise folk were always welcoming new servers into the fold.

              😃

              I want to live in this fairy tale land of new equipment too lol we poor sods in small / charity environments get everyone else's used gubbins.

              BRRABillB 1 Reply Last reply Reply Quote 0
              • BRRABillB
                BRRABill @MattSpeller
                last edited by

                @MattSpeller said:

                I want to live in this fairy tale land of new equipment too lol we poor sods in small / charity environments get everyone else's used gubbins.

                I bet my servers are older than yours! 😉

                scottalanmillerS 1 Reply Last reply Reply Quote 1
                • scottalanmillerS
                  scottalanmiller @BRRABill
                  last edited by

                  @BRRABill at one point we had nearly all ten year old servers 🙂

                  dafyreD 1 Reply Last reply Reply Quote 0
                  • dafyreD
                    dafyre @scottalanmiller
                    last edited by

                    @scottalanmiller said:

                    @BRRABill at one point we had nearly all ten year old servers 🙂

                    @scottalanmiller can still probably top this... But when I was at my last job we finally retired a server that had been in operation for 30 years.

                    1 Reply Last reply Reply Quote 0
                    • BRRABillB
                      BRRABill
                      last edited by

                      I've been working with @mdecamp to size up a UPS for my new DELL T320.

                      Turns out it never draws above 60W while running. These little suckers are efficient these days!

                      What would you need in this thing to get it to its full 495W potential?

                      DashrenderD RojoLocoR 2 Replies Last reply Reply Quote 0
                      • DashrenderD
                        Dashrender @BRRABill
                        last edited by

                        @BRRABill said:

                        What would you need in this thing to get it to its full 495W potential?

                        Fully loaded with RAM, Disk and a tape drive.

                        1 Reply Last reply Reply Quote 1
                        • JaredBuschJ
                          JaredBusch
                          last edited by

                          Video cards

                          1 Reply Last reply Reply Quote 1
                          • RojoLocoR
                            RojoLoco @BRRABill
                            last edited by

                            @BRRABill said:

                            I've been working with @mdecamp to size up a UPS for my new DELL T320.

                            Turns out it never draws above 60W while running. These little suckers are efficient these days!

                            What would you need in this thing to get it to its full 495W potential?

                            A USB hotplate.

                            1 Reply Last reply Reply Quote 0
                            • BRRABillB
                              BRRABill
                              last edited by

                              Are there any USB beer coolers?

                              scottalanmillerS M 2 Replies Last reply Reply Quote 0
                              • scottalanmillerS
                                scottalanmiller @BRRABill
                                last edited by

                                @BRRABill said:

                                Are there any USB beer coolers?

                                yes, I have seen those.

                                1 Reply Last reply Reply Quote 0
                                • M
                                  marcinozga @BRRABill
                                  last edited by

                                  @BRRABill said:

                                  Are there any USB beer coolers?

                                  http://www.amazon.com/ThreeH-Beverage-Refrigerator-Computer-H-UF05Red/dp/B016KQ7X8E/ref=sr_1_12?ie=UTF8&qid=1449684378&sr=8-12&keywords=usb+beer+cooler

                                  My wife bought me something similar as a birthday gift, but I've never tried it. For whatever reason I'm only buying beer in bottles, so it won't fit.

                                  BRRABillB 1 Reply Last reply Reply Quote 0
                                  • BRRABillB
                                    BRRABill @marcinozga
                                    last edited by

                                    @marcinozga said:

                                    http://www.amazon.com/ThreeH-Beverage-Refrigerator-Computer-H-UF05Red/dp/B016KQ7X8E/ref=sr_1_12?ie=UTF8&qid=1449684378&sr=8-12&keywords=usb+beer+cooler

                                    My wife bought me something similar as a birthday gift, but I've never tried it. For whatever reason I'm only buying beer in bottles, so it won't fit.

                                    Hang a couple of those off the server. Maybe we'll get close to that 495W!

                                    MattSpellerM 1 Reply Last reply Reply Quote 0
                                    • MattSpellerM
                                      MattSpeller @BRRABill
                                      last edited by

                                      @BRRABill said:

                                      @marcinozga said:

                                      http://www.amazon.com/ThreeH-Beverage-Refrigerator-Computer-H-UF05Red/dp/B016KQ7X8E/ref=sr_1_12?ie=UTF8&qid=1449684378&sr=8-12&keywords=usb+beer+cooler

                                      My wife bought me something similar as a birthday gift, but I've never tried it. For whatever reason I'm only buying beer in bottles, so it won't fit.

                                      Hang a couple of those off the server. Maybe we'll get close to that 495W!

                                      Hell yes, what good is a single beer

                                      1 Reply Last reply Reply Quote 0
                                      • 1
                                      • 2
                                      • 3
                                      • 4
                                      • 4 / 4
                                      • First post
                                        Last post